MCS BUILD, CLAVERDON – RELOCATION

August 30, 2019

The Client:

Construction company providing building services for residential projects

The Project:

MCS Group are a construction management team of approx. 60 staff previously located in Claverdon, Warwickshire, moving to a new, purpose-built office in Warwick.

The move plan was agreed to relocate in 2 phases to allow testing on the network, and to provide manageable headcount when considering time frame and IT support.

The move was carried out commencing at 4pm on a Friday and completed, including commissioning the IT before start of business on the following Monday.

ABC planned and managed the move process, supported by move partners BMG (Halesowen)

The relocation before inventory included IT, filing, archives and all furniture. ABC had the dedicated support from the MCS “move party” ensuring the relocation was a great success and business connectivity was maintained.